NSW Water Utilities Drought Relief
Two pontoons moving up to 300 ML of fresh water a day to a coffer dam, delivered as a full design and construct drought relief package for an inland NSW water utility.

- Contract value
- $3.8 Million
- Duration
- 6 Months
Equipment
- Containerised switch rooms
- 415 V MCC
- 2x pontoons
- 6x pumps at 660 L/s each
- Pipelines and valving
Description
When drought put pressure on supply, a water utility located in inland NSW needed a complete relief package, fast. We designed, supplied and delivered two pontoons that move up to 300 ML of fresh water a day to a coffer dam, along with a containerised 415 V switch room, heavy-duty trailing cable and a flexible DN600 pipeline.
Our engineering team took on the full design and construct, and we delivered within the timeframe specified, using Australian-made products throughout.
More water management systems projects

Centennial Coal Water Management System

BHP/BMA Tailings Storage Management Project

Mt Owen CHPP Reagent Dosing Station
Planning a similar project?
Design, supply, install and commissioning delivered as one turnkey package, built to Australian and International Standards. A member of our engineering team will respond within 24 hours.