Water Management · Inland NSW

NSW Water Utilities Drought Relief

Two pontoons moving up to 300 ML of fresh water a day to a coffer dam, delivered as a full design and construct drought relief package for an inland NSW water utility.

Crane lowering a pontoon pump station onto a pit lake during drought relief works in inland NSW
Contract value
$3.8 Million
Duration
6 Months

Equipment

  • Containerised switch rooms
  • 415 V MCC
  • 2x pontoons
  • 6x pumps at 660 L/s each
  • Pipelines and valving

Description

When drought put pressure on supply, a water utility located in inland NSW needed a complete relief package, fast. We designed, supplied and delivered two pontoons that move up to 300 ML of fresh water a day to a coffer dam, along with a containerised 415 V switch room, heavy-duty trailing cable and a flexible DN600 pipeline.

Our engineering team took on the full design and construct, and we delivered within the timeframe specified, using Australian-made products throughout.

Planning a similar project?

Design, supply, install and commissioning delivered as one turnkey package, built to Australian and International Standards. A member of our engineering team will respond within 24 hours.