Mining · Moranbah, QLD

BHP/BMA Tailings Storage Management Project

Aqua Energy Group successfully installed this infrastructure project which included the complete design, supply and commission of all electrical and mechanical aspects.

Crane lifting a pontoon pump station with handrailed walkway deck for the BHP/BMA tailings storage project, Moranbah, QLD
Contract value
$2 Million
Duration
18 months

Equipment

  • 2 complete pontoon pump stations
  • Diesel dewatering pump station
  • Fuel pod
  • Substations, transformers, control panels
  • Associated pipework and valving

Description

The project included 2 dual electric pontoons, access walkways, 2 kiosk substations, all mine spec control panels and instrumentation. Aqua Energy Group successfully delivered the challenging project for BHP and provided a full turn-key solution that incorporated all commissioned and integration of electrical and pipework manifolds.

Challenges

  • Operational Mine Site
  • Complex Tailing Project
  • Integration with other Contractors
  • High-end Engineered Solution