Fire & Safety · Cobar, NSW

Cobar Fire Pump Enclosure

Aqua Energy Group was commissioned to complete a diesel and electric fire pump enclosure, complete with muffler, exhaust, and rain cap, for a remote mine site in Cobar, NSW.

Electric fire pumpset with red pipework and control panel on a base frame for the Cobar fire pump enclosure, NSW
Contract value
$250,000
Duration
4 months

Equipment

  • Diesel AS2941-2013 Hydrant/Sprinkler Booster Pump (55 L/s @ 1200 kPa)
  • Electric AS2941-2013 Hydrant / Sprinkler Booster Pump (55 L/s @ 1200 kPa)
  • Jacking Pump System
  • Complete Base Frame

Description

Aqua Energy Group managed everything from civil works through to final commissioning on time and on budget.

Challenges

Remote site location for installation.

Planning a similar project?

Design, supply, install and commissioning delivered as one turnkey package, built to Australian and International Standards. A member of our engineering team will respond within 24 hours.