NSW WATER UTILITIES DROUGHT RELIEF
March 6, 2024
PROJECT
NSW Water Utilities Drought Relief
INDUSTRY
Infrastructure
LOCATION
Inland, NSW Australia
EQUIPMENT
- Containerized Switch Rooms
- 415V MCC
- 2 x Pontoons
- 6x Pumps at 660L/s each pump
- Pipelines and Valving
DURATION
6 months
VALUE
$3.8 Million
DESCRIPTION
The project Included the design, supply, and delivery of two pontoons delivering up to 300ML a day of freshwater to a coffer dam arrangement. The project also consists of a 415V containerised switch room, heavy-duty trailing cable, and a flexi DN600 pipeline arrangement for the two pontoons. This project was a full D&C by the Aqua Energy Group Engineering team.
CHALLENGES
This Project was won by Aqua Energy Group on the merit that we could supply a complete drought relief package in a short time frame. We are proud that we could not only deliver the project in the time frame specified, but we were also able to use all Australian made products.