NSW WATER UTILITIES DROUGHT RELIEF

March 6, 2024

PROJECT

NSW Water Utilities Drought Relief

INDUSTRY

Infrastructure

LOCATION

Inland, NSW Australia

EQUIPMENT

  • Containerized Switch Rooms
  • 415V MCC
  • 2 x Pontoons
  • 6x Pumps at 660L/s each pump
  • Pipelines and Valving

DURATION

6 months

VALUE

$3.8 Million

DESCRIPTION

The project Included the design, supply, and delivery of two pontoons delivering up to 300ML a day of freshwater to a coffer dam arrangement. The project also consists of a 415V containerised switch room, heavy-duty trailing cable, and a flexi DN600 pipeline arrangement for the two pontoons. This project was a full D&C by the Aqua Energy Group Engineering team.

CHALLENGES

This Project was won by Aqua Energy Group on the merit that we could supply a complete drought relief package in a short time frame. We are proud that we could not only deliver the project in the time frame specified, but we were also able to use all Australian made products.