WATER MANAGEMENT EXPERTS

Completed Projects

MT OWEN CHPP REAGENT DOSING STATION

March 6, 2024

PROJECT

Reagent Turnkey Dosing Station

INDUSTRY

Military

LOCATION

Hunter Valley, NSW Australia

EQUIPMENT

2x Double- sided, Custom Designed dosing pump cabinets for hazardous and Non-hazardous fluids, 1x motor Control cabinet

DURATION

9 months

VALUE

$1 Million

DESCRIPTION

Aqua Energy Group were engaged to design, supply, install & commission a complete Reagent Plant to suit our clients requirements. This Project utilises two double sided pump cabinets with a mixture of hazardous–rated and standard dosing pumps to pump set amount of liquid into the thickening plant on site. These cabinets are accompanied by a customised switchboard for full operation of the units. Two large 40FT containerised Fuel storage units were supplied as part of our package, flow-monitoring, all lighting, and complete installation project.

CHALLENGES

Aqua Energy Group was able to navigate very strict environmental requirements and tight timeframe for the customer to get their new coal fines handling plant up and operation ASAP.