WATER MANAGEMENT EXPERTS

Completed Projects

BHP/BMA TAILINGS STORAGE MANAGEMENT PROJECT

February 28, 2023

PROJECT

BHP/BMA Tailings storage management project

INDUSTRY

Mining/Infrustructure

LOCATION

Moranbah, QLD

EQUIPMENT

2 complete pontoon pump stations, a diesel dewatering pump station, fuel pod, substations, transformers, control panels, and all associated pipework and mainfold

DURATION

18 months

VALUE

$2 Million

DESCRIPTION

Aqua Energy Group successfully tended and won this complex tailing infrastructure project which included the complete design, supply and commission of all electrical and mechanical aspects of the project. The project included 2 by dual electric pontoons, access walkways, 2 by kiosk substations, all mine spec control panels and instrumentation. Aqua Energy Group successfully delivered the challenging project for BHP and provided a full Turn-Key solution that incorporated all commissioned and integration of electrical and pipework manifolds.

CHALLENGES

  • Operational Mine Site
  • Complex Tailing Project
  • Integration with other Contractors
  • High End Engineered Solution