PROJECT
Water transfer Pump Station
INDUSTRY
Mining
LOCATION
Midwest, NSW Australia
EQUIPMENT
1x switchroom with accompanying MCC and VSD’s. 3x pump sheds with associated Pipework
DURATION
6 months
VALUE
$1.4 Million
Partnering with our client Aqua Energy Group were contracted to design and manufacture a water transfer pump Station, including a switchroom with 315kW pumps, fed by VSD’s Aqua Energy Group were able to complete the final commissioning and hand over of the project, on time and on Budget.
CHALLENGES
Remote, difficult to access worksite, far from Aqua Energy Group’s main office. Difficult to communicate externally due to limited phone reception.